Although the implementation was originally planned for 30 days, it was later reduced to 25 days by the client. On the evening of the 25th day, the new DCS and ESD were commissioned and gas was successfully charged in the plant.
From Study to Engineering: Designing an Automation Solution From Scratch
The Honeywell team worked closely with the plant staff to manage all aspects of the implementation, including:
- On-site study
- Documentation
- Micro-level planning
- Detail engineering
- Installation and commissioning
Benefits After Implementation of Automation System
With this migration, the unit became capable of improving its energy efficiency as software and logic replaced most of the hardwired systems. The C300 Process Controllers at the ammonia plant use the Control Execution Environment (CEE) software that provides an execution and scheduling environment.