Kuwait: Fabrication Cooec-Fluor Concludes Module Programme for Kipic Al-Zour Project

| Editor: Ahlam Rais

The module programme for the Kuwait Integrated Petroleum Industries Company (Kipic) Al-Zour project in Kuwait was completed by Fluor’s JV Cooec-Fluor fabrication yard in China. On completion, the new complex is expected to be one of the largest refineries across the globe.

Related Company

Cooec-Fluor's fabrication yard shipped the final module assembly and it recently arrived at the project site in Kuwait.
Cooec-Fluor's fabrication yard shipped the final module assembly and it recently arrived at the project site in Kuwait.
(Source: Business Wire)

Texas/USA – Fluor Corporation recently announced that its joint venture Cooec-Fluor Heavy Industries, Co. (Cooec-Fluor) fabrication yard in Zhuhai, China, has safely completed the entire module programme for the Kuwait Integrated Petroleum Industries Company (Kipic) Al-Zour project in Kuwait.

“The Cooec-Fluor yard completed the modular programme over a period of 24 months from the start of steel fabrication to load out of the last modules,” said Chris Vertanness, vice president and director of operations at the yard. “The Cooec-Fluor team has accomplished numerous fabrication and logistics milestones on this project working closely with the Fluor-led joint venture team, and I look forward to continue to show the world what our yard can do.”

To achieve this milestone, Cooec-Fluor delivered 188 modules in 20 separate shipments with a combined weight of 65,000 metric tonnes. In addition, the yard fabricated more than 95,000 pipe spools of carbon, alloy and stainless steel pipe which will be installed by the project team at the site.

Specialist Book „Heat Transfer Technique“The comprehensive standard work „Heat Transfer Technique“ offers not only a detailed and well-founded presentation of the basics of heat transfer technique, but also shows the latest state of the art and the latest regulations in the use of organic fluids. Thematically, the book is rounded off with an overview of property data of organic heat transfer fluids as well as many use cases from practical experience.

Leveraging Cooec-Fluor for fabrication and modular assembly was a key component in the Kipic project’s overall execution strategy. By performing large-scale modularisation at the fabrication yard, field labour at the project site was significantly reduced resulting in greater cost efficiency, enhanced safety performance, and minimised strain on the local labour market.

The project was executed with a relentless focus on health, safety and environmental performance, achieving a total case incident rate of 0.06 and a lost-time injury rate of 0.02. The final module shipment of 8,600 metric tonnes was shipped from Cooec-Fluor and recently arrived at the project site in Kuwait.

Fluor is leading a joint venture that is working to deliver two engineering, procurement, fabrication and construction packages for key process support units, utilities and infrastructure for the Al-Zour refinery project in Kuwait. Upon completion, the new complex is expected to be one of the largest refineries in the world and produce 615,000 barrels of oil per day.