Jacobs Engineering has been selected by BP to provide engineering, procurement and construction management (EPCM) services for the Phase 2 of the Khazzan Project in the Sultanate of Oman.

Related Companies

In September 2017 a significant milestone was reached when Phase 1 of the BP Khazzan Project achieved first gas ahead of schedule.
In September 2017 a significant milestone was reached when Phase 1 of the BP Khazzan Project achieved first gas ahead of schedule.
(Source: BP)

Dallas/USA — Under the terms of the three-year contract, the engineering services provider will continue to deliver engineering, procurement and construction management (EPCM) services in support of the project, including the ongoing expansion of the gas gathering system, wellsite facilities and export pipelines.

Khazzan is considered to be one of the biggest tight gas projects in the Middle East and Phase 1 is expected to develop approximately seven trillion standard cubic feet of gas, deliver plateau production of one billion standard cubic feet of gas per day and 25,000 barrels of gas condensate per day.

In September 2017 a significant milestone was reached when Phase 1 of the BP Khazzan Project achieved first gas ahead of schedule. Jacobs delivered engineering, procurement and construction management (EPCM) services for the process and infrastructure work during the first phase of this greenfield project, through its global integrated delivery model, utilizing knowledge from a diverse group of employees, as well as local construction suppliers.

“Upon completion of the project, this field has the potential to produce gas for Oman for decades to come and simultaneously sets the stage for knowledge transfer and Omanization," said Jacobs Petroleum and Chemicals President Vinayak Pai.